Information about land plots and infrastructure


Free
Busy
Infrastructure

Click on the polygon of the land plot to see its status, area in hectares, and cadastral number.
The working scheme includes 23 sections. The dates of status data are shown in the cards.


Osentsy Playground

Information about infrastructure facilities constructed, under construction, and planned for construction/reconstruction of the Perm Industrial-Industrial Special Economic Zone as of 30.09.2026. Osentsy Playground

Infrastructure facility Object capacity Stage of object creation
Power supply networks 48.7 MW 4.9 MW-the facility has been created; 43.8 MW-construction and installation works are underway at the facility
Water supply networks 1 500 m3 / h 250 m3 / h — the object has been created; 1,250 m3 / h — construction and installation works are underway at the object
Wastewater networks 1 500 m3 / h 250 m3 / h — the object has been created; 1,250 m3 / h — construction and installation works are underway at the object
Heat supply networks 23.2 MW Infrastructure facilities are under construction
Gas supply networks 20,000 m3 / h Infrastructure facilities are under construction
On-site road networks 5.65 km Infrastructure facilities are under construction
Telecommunications networks 5.5 km Infrastructure facilities are under construction

Information on the workload of constructed and (or) reconstructed infrastructure facilities of the Perm Special Economic Zone of Industrial Production Type as of 30.09.2026. Osentsy Playground

Infrastructure facility Object capacity Traffic load*
Power supply networks 4.9 MW 4,08%
Water supply networks 250 m3 / day 0%
Wastewater networks 250 m3 / day 0%

* Availability of concluded technical connection agreements and (or) resource supply agreements.


Towboat platform

Information about infrastructure facilities constructed, under construction, and planned for construction/reconstruction of the Perm Industrial-Industrial Special Economic Zone as of 30.09.2026. Towboat platform

Infrastructure facility Object capacity Stage of object creation
Power supply networks 1.97 MW Item created
Water supply networks 86.4 m3 / day Item created
Wastewater networks 86.4 m3 / day Item created
Gas supply networks 214.5 m3 / h Item created
On-site road networks 830 m Item created

Information on the workload of constructed and (or) reconstructed infrastructure facilities of the Perm Special Economic Zone of Industrial Production Type as of 30.09.2026. Towboat platform

Infrastructure facility Object capacity Traffic load*
Power supply networks 1.97 MW 70%
Gas supply networks 214.5 m3 / h 75%
Water supply networks 86.4 m3 / day 65%
Wastewater networks 86.4 m3 / day 65%

* Availability of uploaded contracts and / or contracts for resource delivery.


Upper Mullahs Playground

Information about infrastructure facilities constructed, under construction, and planned for construction/reconstruction of the Perm Industrial-Industrial Special Economic Zone as of 30.09.2026. Upper Mullahs Playground

Infrastructure facility Object capacity Stage of object creation
— — —

Information on the workload of constructed and (or) reconstructed infrastructure facilities of the Perm Special Economic Zone of Industrial Production Type as of 30.09.2026. Upper Mullahs Playground

Infrastructure facility Object capacity Traffic load*
— — —

Information on land plots located within the boundaries of the Special Economic Zone of industrial and industrial type "Perm" and not leased as of 30.09.2026.

List of land plots
Cadastral number Area m2
Osentsy Playground
59:32:3960006:7404 1 273 459
59:32:3960006:7859 93 746
59:32:3960006:7710 221 308
59:32:3960006:7890 58 241
59:32:3960006:7711 18 590
59:32:3960006:7712 17 310
59:32:3960006:8141 13 802
59:32:3960006:8143 14 261
Upper Mullahs Playground
59:01:4716141:204 450 391
59:01:4716141:40 5 109
59:01:4716141:41 280 376
59:01:4716141:43 43 010
Towboat platform
59:01:1717065:53 57 802
59:01:1717065:754 66 192
59:01:1717065:755 130 361